Land Acquisition For Havelian-Thakot Section Of CPEC Project In Final Stages: Senate Told
Sumaira FH Published July 29, 2016 | 01:01 PM
ISLAMABAD,(UrduPoint / Pakistan Point News - 29th july,2016) : Minister for Parliamentary Affairs Sheikh Aftab said Friday land acquisition for construction of Havelian-Thakot section of China Pakistan Economic Corridor (CPEC) project was in final stages. Speaking in the Senate during question hour, the minister said the Chinese company-M/ s China Communication Construction Company had started construction of contractor’s camps at various locations. He said the contractor was under mobilization and the construction work would start shortly after completion of mobilization formalities and would be completed within stipulated time period of 42 months. Answering another question, the minister said a proposed length of the road from Taxila to Haripur via Khanpur was 42 km.
He said one single span bridge was under construction. For remaining portion 13 Kms, the minister added design had been completed and required fund allocation approved.
He said tendering process had been started, adding it may take minimum four months for execution of desired work. Replying to another question, the minister said National Highway Authority (NHA) had only undertaken ShatialThor Nullah Bypass Project as deposit work from (WAPDA), other infrastructure including access roads are being executed by WAPDA.
He said the bypass will be required after construction of Dam and its reservoir and construction of project had already been started with progress 30 progress. The compeletion date was May 22, 2016 but the work on the project was halted mainly due to boundary dispute between KPK and GB Regions since September 16, 2015.
Similarly, he added there were land Acquisition issues. He said NHA had conducted various meetings with WAPDA and other stakeholders various options were being considered to resume construction activities.
Related Topics
Recent Stories
President Raisi leaves for Iran from Karachi
Currency Rate In Pakistan - Dollar, Euro, Pound, Riyal Rates On 24 April 2024
Today Gold Rate in Pakistan 24 April 2024
Punjab CM inaugurates Pakistan’s first Virtual Women Police Station
Dutch model Donny Roelvink embraces Islam
Experts raise concerns over introduction of 10-stick packs
Iranian president arrives in Karachi
Law Minister expresses Govt's resolve to address issue of missing persons
Rizwan’s batting order may be changed: Sources
Nawaz Sharif to visit Guangzhou exhibition in China
FM Dar not traveling to China: Foreign Office
PM takes notice of deliberate delay in tax cases
More Stories From Pakistan
-
Steps under way for expediting cotton cultivation
9 minutes ago -
DC, MPA visited Mianwali Bangalow
9 minutes ago -
IG jail Punjab pays his annual visit
10 minutes ago -
President Raisi leaves for Iran from Karachi
30 minutes ago -
Iranian President leaves after 3-day Pakistan visit
39 minutes ago -
Iranian President reiterates commitment to promote bilateral relation with Pakistan
10 hours ago
-
KP CM chairs meeting of Integrated Security Architecture’s apex committee
11 hours ago -
President Raisi accorded warm welcome on arrival in Karachi
11 hours ago -
Spending quality time in nature may lower heart disease, diabetes risk: Study
11 hours ago -
President Raisi pays respects at Quaid's mausoleum
12 hours ago -
FM Dar speaks to overseas Pakistanis via Zoom
12 hours ago -
Govt to form parliamentary committee to end violence in Balochistan: CM Bugti
12 hours ago