US Audit Faults NASA For Failing To Detect Early Signs Of Schedule Delays For Moon Landing
Fahad Shabbir (@FahadShabbir) Published September 19, 2019 | 12:20 AM
WASHINGTON (UrduPoint News / Sputnik - 19th September, 2019) NASA's push to return humans to the Moon by 2024 is threatened by a failure to account for schedule delays and cost overruns, the General Accountability Office said in a report on Wednesday.
"For example, NASA should enhance contract management and oversight to improve program outcomes," the report said. "NASA's past approach in this area has left it ill-positioned to identify early warning signs of impending schedule delays and cost growth or reap the benefits of competition."
The report recommended that NASA provide sufficient cost and schedule reserves to address unforeseen risks, and also begin producing "realistic cost estimates and assessments of technical risk."
"NASA has historically provided little insight into the future cost of these human spaceflight programs, limiting the information useful to decision makers," the report said.
NASA's goal of sending two humans to the Lunar south pole by 2024 depends on the successful completion and integration of three systems, the giant SLS [Space Launch System] rocket, the Orion crew capsule and the ground control unit, the release said.
NASA senior leaders have acknowledged that the agency is unlikely to meet previously revised 2020 test launch date, while the GAO report warned that issues uncovered during integration and testing may push the date as late as June 2021.
In addition, GAO estimated that NASA's calculations of cost growth for the Space Launch System program is understated by more than $750 million.
At President Donald Trump's insistence, NASA set a 2024 deadline for the first human flight to the Moon since the final Apollo 17 mission in December 1972 - four years earlier than originally planned.
Related Topics
Recent Stories
UAF to ink MoU with Ethiopian universities
Scouts playing exemplary role in serving humanity: Dr Iqrar
Punjab Police cricket honored with shields, medals & CCI certificates
Bugti issues directives to operate circular road parking plaza
PML-N to become more strong under Nawaz Sharif: Rana Sanaullah
300 raids conducted on hideous of drug-dealers
IP rights crucial in achieving SDG : Jam Kamal
Commissioner urges effective action against electricity theft
PAK-EPA's clean lab boosts environmental analysis capabilities with advanced ICP ..
Romania court opens way for start of influencer Tate's trial
Japan International Cooperation Agency (JICA) delegation visits WSSCA
13 outlets sealed for violating Hepatitis preventive SOPs
More Stories From World
-
Romania court opens way for start of influencer Tate's trial
18 minutes ago -
Kenya flood death toll since March climbs to 70
18 minutes ago -
At least 10 people killed in Brazil fire: officials
18 minutes ago -
Russia targets Ukraine railways as Western aid due to arrive
51 minutes ago -
Miner Anglo American rejects BHP's near $39-billion takeover bid
1 hour ago -
At least 10 people killed in Brazil fire: officials
60 minutes ago
-
Junta-led Burkina Faso suspends BBC, Voice of America for two weeks
60 minutes ago -
Saudi to host top Arab, EU diplomats for Gaza talks: officials
1 hour ago -
Kenya flood death toll since March climbs to 70: govt
58 minutes ago -
US Fed's favored inflation measure accelerates in March
2 hours ago -
Kenya flood death toll since March climbs to 70: govt
2 hours ago -
Russia striking Ukraine railways to 'paralyse' army cargo: Ukraine source
2 hours ago